Delivering on major sporting events with their immutable deadlines, record budgets and immense public scrutiny is certainly a feat in of itself. MIGSO-PCUBED shares insights from our experience delivering the London 2012 Olympics – applicable to any critical project or program.
MIGSO-PCUBED has gained significant expertise in our years of service in organizing world class sporting events. We have had the pleasure to work on two Olympic Games, Athens and London. In addition we have worked on the World Cup, the Commonwealth Games and Formula 1 racing.
With high profile events such as these nothing can be left to chance – the eyes of the world comment on every aspect. A country’s reputation rests on its successful execution with deadlines that cannot move and very diverse stakeholders who need to be engaged and supportive over the many years it takes to deliver these awe inspiring events.
London 2012 was particularly challenging as it garnered significant international attention and a visible lack of support from the press/public opinion at the onset. However as preparation for the games evolved, support for the event increased, resulting in one of the most financially successful games delivered, as well as a well-planned legacy of long term benefits.
Delivering a major sporting competition is about far more than the act of organizing the event itself; it puts the reputation of a whole country on the line. First perceived as an issue, the deadline of July 2012 became an asset to design a comprehensible 7 years program. It was also a very useful argument when it came to make stakeholders move onward and get on with the project.
“(MIGSO-PCUBED was the) supplier of programme management consultancy services (ODA) to the London 2012 Games.”
- British Olympic Association
Seven years of preparation is a long time to be getting ready for an event. As a matter of fact success needed to be identified at key stages. Each year 10 milestones were chosen in order to maintain momentum, clarity and confidence. Another tool was making good use of pamphlets and professional looking communications to publicize the achievement of key milestones, rather than emails.
Read also: What is PMO? A Complete Guide.
With the same objective, the Basketball Arena was designed to be easily dismantled post games. Additionally, the Olympic athlete housing has been converted to desperately needed additional apartments in a city where rental rates are quite high.
The governance of the event counted approximately 30 stakeholders and each could legitimately slow down the execution. Therefore, it was essential to build a close and strong relationship with each of them thanks to which decisions would be taken and efficiently executed in the shortest possible time. Preparation for meetings were critical where attendees reviewed and discussed materials ahead of the meetings so that actionable decision could be made quickly with the broader group.
Another important aspect was the diversity of requirements, initially some members were concerned decisions were being overly influenced by the strongest personalities of the group. The solution was to draw up seven clear and objective criteria to take into account all the factors involved with each project business case. Therefore, requirements such as treasury and sustainability requirements could coexist with equal importance.
A study carried out by our organization a few years ago into why Telecommunications projects were suffering from delays and overruns showed that if people were not taking ownership of the overall project it would get stuck at key gateways.
Indeed, people were only looking at their own silo. Shifting everyone to think like they owned the business and final outcome was essential. It was important to give people cross functional objectives as part of a team, and across different teams to achieve this.
Making people think like an owner guaranteed that nothing was left to chance.
A good example is the Acerlor Mittal Orbit which was a venue itself. There was no meaningful budget allocated for Arts, however, two project team members did not take no for an answer and developed an entrepreneurial workaround to obtain sponsorship.
To ensure the successful delivery of a major sporting event you need to build a robust system of pre-agreed processes and responsibilities. It was important to be very clear on the baseline in order to avoid costly mistakes during the process. Even if it took time, it was preferable to scrutinize the different delivery options at the early stage in order to avoid changes once the project took off.
Roles of the delivery organization and the interaction within the organization (ODA, Delivery Partners and Supply Chain) were clearly defined thanks to tools like cross project assurance and cross project governance. This organizational definition allowed everyone to give the best of themselves.
Finally, for London 2012, quantifiable risk assessments were carried out to allocate how much contingency funding projects should be allocated as a percentage of their overall cost. Risk was at the heart of the decision making not unlike many large IT projects. This greatly helped project managers accomplish their tasks. Teams could deal with the unexpected and be flexible. If risk did not materialize then money was recaptured into program contingency fund.
This article was written by Ky Nichol.
Loved what you just read?
Let's stay in touch.
No spam, only great things to read in our newsletter.
We combine our expertise with a fine knowledge of the industry to deliver high-value project management services.
MIGSO-PCUBED is part of the ALTEN group.
Find us around the world
Australia – Canada – France – Germany – Italy – Mexico – The Netherlands – Portugal – Romania – South East Asia – Spain – Switzerland – United Kingdom – United States
© 2024 MIGSO-PCUBED. All rights reserved | Legal information | Privacy Policy | Cookie Settings | Intranet
Perfect jobs also result from great environments : the team, its culture and energy.
So tell us more about you : who you are, your project, your ambitions,
and let’s find your next step together.
Dear candidates, please note that you will only be contacted via email from the following domain: migso-pcubed.com. Please remain vigilant and ensure that you interact exclusively with our official websites. The MIGSO-PCUBED Team
Choose your language
Our website is not supported on this browser
The browser you are using (Internet Explorer) cannot display our content.
Please come back on a more recent browser to have the best experience possible